Both parties breached the contract. Trial court found Semac breached by abandoning the project, but Skanska also breached by failing to provide a 48-hour cure period before termination. Skanska awarded $3,857,130.77 in damages for overpayment, but Semac entitled to termination payment calculated by percentage of project completion.
The plaintiff subcontractor, E Co., sought to recover damages from the defendant, S Co., for, inter alia, breach of contract in connection with a dispute arising from a project relating to the expansion and renovation of a hospital. Pursuant to its contract with S Co., E Co. agreed to perform all electrical work for the project. The contract provided that E Co. had a duty to coordinate with S Co., that E Co. had made allowances for all hindrances and delays to its work, and that E Co. would work within S Co.'s schedule, which S Co. may revise from time to time. S Co. had the right to direct a change in E Co.'s work on written notice and, during the course of the project, thirty-eight change orders were issued. After several months, E Co. sent S Co. a notice, alleging a cardinal change to the contract due to issues that arose during the preceding months and asserting that it could only continue to perform under the contract if S Co. agreed to additional financial terms. S Co. responded that E Co.'s refusal to proceed under the contract constituted default and, the next day, S Co. terminated E Co. E Co. alleged that S Co. had breached the contract by its wrongful termination of E Co., and S Co. filed a counterclaim, alleging, inter alia, breach of contract. S Co. also filed a third-party complaint against K and T, the chief financial officer and president of E Co., respectively, alleging, inter alia, fraudulent conduct. The case was tried to the court, which rendered judgment in part for S Co. on its counterclaim, and in favor of K and T on the third-party complaint. On S Co.'s appeal and E Co.'s cross appeal to this court, held: 1. The trial court properly rejected E Co.'s claim that there had been a cardinal change in the contract terms and properly concluded that E Co. breached the contract by abandoning the project: the court properly focused on the nature and impact of the delays on the work expected of and performed by E Co., which were not extraordinary in a pr
This summary was generated to explain the ruling in plain English and is not legal advice.
Court rulings like this one are useful, but every situation is different. Take 2 minutes to see which laws may protect you — it's free, private, and no account is required to start.
This ruling information is sourced from public court records via CourtListener.com. It is provided for informational and educational purposes only and does not constitute legal advice.